| Task Category | Tasks | Week |
| FOUNDATION | excavation | #1 #2 #3 |
| form footings | ||
| place footing concrete | ||
| install drainage and stone | ||
| lay block | ||
| install downspout leaders | ||
| set steel | ||
| brace foundation walls | ||
| backfill | ||
| FRAMING | #4 #5 #6 #7 |
|
| 1st Floor deck | ||
| 1st Floor walls | ||
| 2nd Floor deck | ||
| 2nd Floor walls | ||
| set trusses | ||
| sheath roof | ||
| ENCLOSURE | #7 #8 #9 |
|
| install roof | ||
| install Dow board | ||
| build porches | ||
| install windows and doors | ||
| box out driveway | ||
| rough elecrical | ||
| rough heating | ||
| rough plumbing | ||
| EXTERIOR FINISHES | #10 #11 |
|
| install siding | ||
| install gutters | ||
| INTERIOR WORK | #12 #13 #14 #15 |
|
| install insulation | ||
| hang drywall | ||
| finish drywall | ||
| stipple drywall | ||
| INTERIOR FINISHES | #16 #17 |
|
| prime entire house | ||
| finish paint kit. & baths | ||
| install. kit. & bath | ||
| install trim package | ||
| caulk and spackle | ||
| INTERIOR FINISHES (cont'd) | #18 #19 |
|
| finish paint | ||
| finish electrical | ||
| finsih heating | ||
| install hardware |