Proposed Construction Schedule

Task Category Tasks Week
FOUNDATION excavation #1
#2
#3
  form footings
  place footing concrete
  install drainage and stone
  lay block
  install downspout leaders
  set steel
  brace foundation walls
  backfill
FRAMING   #4
#5
#6
#7
  1st Floor deck
  1st Floor walls
  2nd Floor deck
  2nd Floor walls
  set trusses
  sheath roof
ENCLOSURE   #7
#8
#9
  install roof
  install Dow board
  build porches
  install windows and doors
  box out driveway
  rough elecrical
  rough heating
  rough plumbing
EXTERIOR FINISHES   #10
#11
  install siding
  install gutters
INTERIOR WORK   #12
#13
#14
#15
  install insulation
  hang drywall
  finish drywall
  stipple drywall
INTERIOR FINISHES   #16
#17
  prime entire house
  finish paint kit. & baths
  install. kit. & bath
  install trim package
  caulk and spackle
INTERIOR FINISHES (cont'd)   #18
#19
  finish paint
  finish electrical
  finsih heating
  install hardware